Summer Works
20 August 2014

Improvements continue at the Paramount Court.  The schedule of works include brick cleaning, painting, brick work and pointing of the front facade.  The works are scheduled to finish in September.

The last report from the main contractor:

We have instructed replacement of part of the University Street parapet which has suffered from movement.  This work is underway. We hope to have the scaffolding down on University Street around 12th September. This is approx. 2 weeks behind the programme reflecting the early bad weather during the scaffolding erection and for select window replacement works by tenants.

The Tottenham Court Road work is well underway and the same parapet wall works will be required across the whole face with repointing of the lower parapets. We have installed a mesh product to the front face of the balconies to address the haphazard cracking defect. The team continues to work hard to maintain schedule